    Underwater Sheet Pile Welding Wightlink Ferry Terminal

    MMC Divers complete Underwater grinding, cutting and burning on the Wightlink ferry berth in the New Forrest Lymington.

MMC UNDERWATER SHEET PILE WELDING WIGHTLINK FERRY TERMINAL

Client: Wightlink

Contractor: MMC Diving Services

Date posted: 11-03-2022

Following a conditional survey undertaken by Aecom utilising our dive team, MMC Diving services were fortunate enough to win the tender to undertake the underwater welding works on the Wightlink freshwater ferry berth in Lymington New Forest, the project involved repairing holes within the sheet piles retaining wall and cleaning up all 88 tie rod bolts for a conditional survey, then welding on removable grease boxes to protect and lengthen the life of the wall as part of Wightlink's asset management plan.

Our seven-man strong cross trained team of rope access engineers and coded welders completed the project ahead of schedule saving time and money for our client enabling the freshwater berth to resume essential day to day activities.

This project involved tidal works, NDT thickness testing above and below the water welding and grinding, survey and report writing.

[Return to case studies]

Royal Institute Of Navigation Association of Diving Contractors UK Health and Safety Executive Construction Line Royal Society for the Prevention of Accidents accredited Achilles UVDB Sea Start Offical Divers Buy With Confidence Sea Shield Approved Applicators HCL Clamping Solutions Joscar Registered Cyber Essentials